What is the difference between Total Float and Free Float in Primavera P6. … Total Float: is the amount of time an activity can be delayed without delaying the Project Finish Date. Free Float: is the amount of time an activity can be delayed without delaying its Successor Activity Finish Date.
What is a float in Primavera?
What is the difference between Total Float and Free Float in Primavera P6. … Total Float: is the amount of time an activity can be delayed without delaying the Project Finish Date. Free Float: is the amount of time an activity can be delayed without delaying its Successor Activity Finish Date.
What is float in schedule?
Learn that Total Float is the amount of time that a task or activity in a schedule can be delayed without causing a delay to subsequent activities and the project completion date.