It is calculated from the project budget. For example, if the actual percent complete is 75% and the task budget is $10,000, BCWP = 75% x $10,000 = $7,500.
How do you calculate Bcwp and ACWP?
It gives you a quick look at where you are against budget at any given point.
- BCWS = % Complete (Planned) x Project Budget.
- BCWP = % Complete (Actual) x Project Budget.
- Cost Variance = BCWP – ACWP.
- CPI = BCWP / ACWP.
How is ACWP calculated in MS project?
As progress (percentage of completion or actual work) is reported on the task, Microsoft Office Project calculates ACWP. This is the cost of actual work plus any fixed costs for the task to date. ... If you prefer, you can have ACWP calculated based on your entries in the Actual Cost (timephased) field.